Pavement Repair

FY 18/19 Arterial/Collector Pavement Repair – Phase I

SWP performed milling and/or pulverizing, pavement preparation, paving, and striping/pavement markings.

202 Milling – 285,000 SY, 404 Asphaltic tack coat CSS-1h 1:1 – 175 Ton, 406 Asphaltic concrete PAG#2 (arterial) – 32,000 Ton, 406 Bituminous adjustment (if applicable) – 10,000 USD, 406 Fuel adjustment (if applicable) – 2,500 USD, 509 Adjust sewer MHs – 55 EA, 510 Adjust water valves – 133 EA, 701 Maintenance & protection of traffic – 1 LS, 701 Uniformed law enforcement services – 700 Hrs, 704 Pavement markings, symbols, legends, raised markers, and detection loops – 1 LS, Mobilization – 1 LS, 909 Adjust survey monuments – 47 EA, 924 Miscellaneous work – 100,000 USD