Mirror Lake Trailhead Relocation
SWP was awarded this contract by the Western Federal Lands Division of FHWA to complete a widening and improvement project on Oregon DOT 26.
Project Work Included:
- Mill and fill for 3,390 Ton of an ODOT Type 1
- Asphalt Concrete Pavement
- Guardrail placement
- Sign systems
- Delineators
- Rumble strip
- Pavement markings
- ITS sign system.
- Fixture replacements
- Trash receptacle
- Bicycle storage racks
- Picnic table
- Vault toilet
- Stairways
- Handrail
- Pedestrian rail
- Trail kiosk
The trailhead parking lot was expanded to accommodate 22 additional parking spaces utilizing a welded wire face and a mechanically stabilized earth wall.
SWP removed and replaced nine (9) structural timber and lumber pressure treated pedestrian bridges.